April 2017

Land Purchase

American Royal takes a major step toward its new home by acquiring 47 acres west of 118th. This land purchase sets the foundation for a purpose-built campus in Kansas City, Kansas.

July 2019

80 Acres Secured

This adjacent land acquisition, executed via the Patterson Family Foundation, signaled private donor support enabling a more cohesive site plan that now spans nearly 200 acres.

December 2019

Site Officially Announced

American Royal signs a 99-year lease on land from the Patterson Family Foundation and hosts a public sign planting ceremony, officially announcing the future location of the new campus.

Oct 2019 – Apr 2020

Zoning & Planning

American Royal works with the Unified Government of Wyandotte County to complete zoning, preliminary, and final development plan approvals for the new site.

May 2020

COVID-19 Pause

Due to the uncertainty caused by the COVID-19 pandemic, all development activity on the new campus is paused to assess future event feasibility.

May 2020

Festival Grounds Acquired

Despite the pause, American Royal purchases an additional 77 acres for future outdoor event use, laying the groundwork for robust community programming.

July 2021

Strategic Planning Begins

The Board of Directors launches a forward-thinking strategic planning process to define the future of the American Royal and its role in agriculture education and entertainment.

June 2022

Plan Approved

The Board approves a new Strategic Plan, including a fresh mission, vision, and purpose. This update re-centers the project around long-term impact.

June 2022

Campus Rebooted

With a new strategic plan in place, the Board directs staff to formally reengage on development of the new campus project.

December 2022

Execution Plan Approved

The Executive Committee approves the internal work plan that will implement the strategic direction, turning planning into action.

July 2022 – Present

Design Revisions

Design revisions begin to align the campus with purpose-driven goals and respond to significant construction cost escalation.

March 2023

Final Plan Approved

The revised final development plan for the campus receives full approval, officially launching the next stage of development.

March 2023

Site Work Begins

Construction officially begins on the new American Royal campus in Kansas City, Kansas with grading and site prep activities.

November 2023

First Steel Raised

The American Royal celebrates a major milestone with its 'barn raising' event as the first piece of steel is anchored into the ground.